 / Home / Bond / Bond Status Report

1998
Project Original
Budget
Current
Budget
Increase
(Decrease)
Status Notes
New Schools
Warren HS$42,662,471$50,356,223$7,693,752C1
Rawlinson MS$22,470,338$26,349,714$3,879,376C1
Burke ES$9,943,748$8,960,287$-983,461C2
Nichols ES$10,504,934$10,490,199$-14,735C1
Rhodes ES$10,504,934$11,881,606$1,376,672C1
Raba ES$10,452,548$9,619,552$-832,996C2
Lewis ES$10,733,141$11,302,272$569,131C1
Sites$1,000,000$1,100,000$100,000C3
Additions / Renovations
Clark HS$1,076,988$1,438,732$361,744C4
Health Careers HS$878,437$1,194,854$316,417C1
Jay HS$1,042,130$2,796,606$1,754,476C10
Marshall HS$2,036,350$1,197,216$-839,134C5
Jones MS$1,734,536$2,874,222$1,139,686C6
Rayburn MS$4,096,238$8,112,297$4,016,059C6
Sul Ross MS$1,052,884$1,010,164$-42,720C8
Cable ES$3,856,201$3,933,468$77,267C7
Cody ES$3,454,410$3,370,433$-83,977C8
Locke Hill ES$3,430,627$3,720,656$290,029C7
Valley Hi ES$3,058,265$5,150,820$2,092,555C6
Portables$0$44,347$44,347C12
Central Office$856,878$823,927$-32,951C8
Language Labs$1,246,300$1,312,642$66,342C1
Kitchen Renov/AC$1,000,000$2,032,093$1,032,093C6
Voc Shop Renov$1,088,555$1,337,327$248,772C6
Infrastructure$49,819,087$52,719,283$2,900,196C1
Technology$26,000,000$26,000,000$0C0
Warehouse Facility$0$1,135,774$1,135,774C11
Allowance - 2001 Bond$0$88,915$88,915C0
Total$224,000,000$250,353,629$26,353,629
Status Codes
D = In Design
B = Bidding
UC = Under Construction
C = Complete

Notes
1. Increased cost was due to inflation in the construction market well in excess of the conservative 3% rate used in establishing the project budget.

2. The decrease was due to a favorable bid. This project was also in the first group of projects bid. This bid occurred before the onset of excessive inflation.

3. The increase was due to unfavorable site costs

4. This project, scheduled late in the 1998 Bond Program, was merged with an addition/renovation project scheduled early in the 2001 Bond Program. The budget reflects the 1998 funds reserved for the merged project. This budget includes inflation costs. See the 2001 Bond Program for additional cost data.

5. The 1998 Bond Program included funds for two major projects at Marshall HS: renovations to Boys' PE and athletic facilities and HVAC replacements. The HVAC replacements were funded under the "infrastructure" category. They have been completed. The Boys' PE/athletic renovation project, scheduled late in the 1998 Bond Program, was merged with other renovation/addition projects, scheduled early in the 2001 Bond Program (including provision of language labs and an auxiliary gym). The amount shown represents funds from the 1998 Bond Program assigned to the total cost of the merged projects. See the 2001 Bond Program table for additional cost information.

6. Increased cost was due to inflation in the construction market well in excess of the conservative 3% rate used in establishing the project budget. Also, the project was extremely complex, and the true costs were underestimated (even without the impact of inflation).

7. The increase was due to a slightly unfavorable bid.

8. The decrease was due to a slightly favorable bid.

9. The 2001 Bond Program approved by voters included $26,356,540 to address the excessive inflation which impacted projects in the 1998 Bond Program.

10. This project, scheduled late in the 1998 Bond Program, was merged with an addition/renovation project scheduled early in the 2001 Bond Program. The budget reflects the 1998 funds reserved for the merged project. This budget includes inflation costs. See the 2001 Bond Program for additional cost data. Additional funding provides for exterior wall restoration.

11. Savings from project were utilized for this project, which was originally to be funded from earned interest, if available.

12. Due to additional growth in enrollment, some older portables are in need of remodeling in order to extend their service as functional space.



Search RSS Contact Us

Northside Independent School District
5900 Evers Rd. • San Antonio, TX 78238-1699
(210) 397-8500 • Contact Us
Texas Education Agency : Recognized District

XHTML 1.1CSS
© Copyright 2009, All Rights Reserved
Communications Dept. • Acceptable Use Policy