| 2001 | ||
|---|---|---|
| Project | Budget | Status |
| Allowance / Contingency | $11,191 | |
| Auditorium seats at Clark & Jay | $225,967 | Complete |
| Bond Issuance Costs | $1,199,759 | 100% Expended |
| Bond Management Costs | $4,152,746 | 100% Expended |
| Food Service Warehouse Renovation | $614,055 | Construction |
| Grissom Road Annex (Student Services) | $963,193 | Complete |
| Maintenance Shop Expansion | $50,661 | Project Delayed |
| North Transportation Satellite | $1,586,372 | Complete |
| Provide Marshall Soccer Field | $69,277 | Complete |
| South Transportation | $238,584 | Complete |
| Support Service Center | $4,668,282 | Complete |
| Transportation - Culebra Station | $1,787,799 | Complete |
| Total | $15,567,886 | |