"Bandera Road North area" ES
2012
$
21,000,000
0%
Under Design
Project Details
Site Address
TBD
Start
/
End
/2012
Architect
Contractor
Client / Contact
Cost
$ 21,000,000
Progress
0%
Related Links
"Westwinds area" ES
2011
$
21,000,000
0%
Under Design
Project Details
Site Address
TBD
Start
/2010
End
/2011
Architect
PBK Architects
Contractor
Client / Contact
Marilyn Sevedge
Cost
$ 21,000,000
Progress
0%
Related Links
Behlau ES
2010
$
19,638,000
13%
Design Concept
Project Details
Site Address
2400 Grosenbacher Road
San Antonio, TX 78245
Start
10/2008
End
5/2010
Architect
Noonan Rittimann
Contractor
Kunz Construction
Client / Contact
Marilyn Sevedge
Cost
$ 19,638,000
Progress
13%
Related Links
Brennan HS
2010
$
89,404,855
58%
Design Concept
Project Details
Site Address
2400 Cottonwood Way
San Antonio, TX 78253
Start
12/2007
End
6/2010
Architect
Marmon Mok
Contractor
Bartlett-Cocke
Client / Contact
Ceasar Ponce, AIA
Cost
$ 89,404,855
Progress
58%
Related Links
Briscoe MS
2010
$
40,997,024
34%
Design Concept
Project Details
Site Address
4265 Lone Star Parkway
San Antonio, TX 78253
Start
8/2008
End
5/2010
Architect
PBK Architects
Contractor
Bartlett-Cocke
Client / Contact
Marilyn Sevedge
Cost
$ 40,997,024
Progress
34%
Related Links
Hector Garcia MS
2009
$
39,142,776
84%
Design Concept
Project Details
Site Address
14900 Kyle Seale Parkway
San Antonio, TX 78255
Start
9/2007
End
6/2009
Architect
Noonan Rittimann
Contractor
Joeris
Client / Contact
Thomas Curiel
Cost
$ 39,142,776
Progress
84%
Related Links
Hoffmann ES
2009
$
18,989,265
96%
Design Concept
Project Details
Site Address
12118 Volunteer Parkway
San Antonio, TX 78253
Start
10/2007
End
5/2009
Architect
PBK
Contractor
Bartlett-Cocke
Client / Contact
Marilyn Sevedge
Cost
$ 18,989,265
Progress
96%
Related Links
Kuentz ES
2009
$
19,900,298
97%
Design Concept
Project Details
Site Address
12303 Leslie Road
Helotes, TX 78023
Start
12/2007
End
6/2009
Architect
O'Neill, Conrad, Oppelt
Contractor
Bartlett-Cocke
Client / Contact
Thomas Curiel
Cost
$ 19,900,298
Progress
97%
Related Links
Langley ES
2009
$
19,288,661
81%
Design Concept
Project Details
Site Address
600 Stevens Parkway
San Antonio, TX 78253
Start
2/2008
End
6/2009
Architect
Garza Bomberger
Contractor
Bartlett-Cocke
Client / Contact
Kathy Weaver
Cost
$ 19,288,661
Progress
81%
Related Links
Lieck ES
2011
$
21,000,000
0%
Under Design
Project Details
Site Address
TBD
Start
/2010
End
/2011
Architect
Noonan Rittimann
Contractor
Client / Contact
Tom Curiel
Cost
$ 21,000,000
Progress
0%
Related Links
Martin ES
2010
$
19,292,675
9%
Design Concept
Project Details
Site Address
730 Canterbury Farm
San Antonio, TX 78228
Start
10/2008
End
5/2010
Architect
Alamo Architects
Contractor
Joeris, Inc.
Client / Contact
Leroy San Miguel & James Berg, AIA
Cost
$ 19,292,675
Progress
9%
Related Links
* Figures Represent General Construction Costs Only
Contact Us for additional information about NISD Bonds.
John Paul Stevens High School

NISD voters have approved four bond packages since 1998 totaling $1.9 billion dollars. With that, the construction of 39 new schools has been completed, begun, or been planned for.

NISD is growing by approximately 4,000 students per year, and 50% of all new homes built in Bexar County are being built here in Northside.

School names that are not finalized are working names only. If you would like to submit a nomination to name a school, please fill out our online Name A School Nomination Form or call NISD at 397-8770 for more information.

Place your mouse cursor over a project to see the project details.
Search RSS Contact Us

Northside Independent School District
5900 Evers Rd. • San Antonio, TX 78238-1699
(210) 397-8500 • Contact Us
Texas Education Agency : Recognized District

XHTML 1.1CSS
© Copyright 2009, All Rights Reserved
Communications Dept. • Acceptable Use Policy