Facility / Campus
Opens
Cost*
Progress
"Alamo Ranch area" MS
2010
$
40,000,000
0%

Project Details
Site Address
4265 Lone Star Parkway
San Antonio, TX 78253
San Antonio, TX 78253
Start
8/2008
End
5/2010
Architect
PBK Architects
Contractor
Bartlett-Cocke, Inc.
Client / Contact
Marilyn Sevedge
Cost
$ 40,000,000
Progress
0%
Related Links
"Bandera Road North area" ES
2011
$
21,000,000
0%

Project Details
Site Address
TBD
Start
/
End
/2011
Architect
Contractor
Client / Contact
Cost
$ 21,000,000
Progress
0%
Related Links
"Canterbury Farm area" ES
2010
$
17,500,000
0%

Project Details
Site Address
TBD
Start
10/2008
End
5/2010
Architect
Alamo Architects
Contractor
Joeris, Inc.
Client / Contact
Victor G. Valdez
Cost
$ 17,500,000
Progress
0%
Related Links
"Kallison Ranch area #1" ES
2010
$
18,500,000
0%

Project Details
Site Address
TBD
Start
/
End
/2010
Architect
Contractor
Client / Contact
Cost
$ 18,500,000
Progress
0%
Related Links
"Laurel Mountain Ranch area" ES
2010
$
19,000,000
0%

Project Details
Site Address
TBD
Start
10/2008
End
5/2010
Architect
Noonan Rittimann
Contractor
Client / Contact
Marilyn Sevedge
Cost
$ 19,000,000
Progress
0%
Related Links
"Westwinds area" ES
2011
$
21,000,000
0%

Project Details
Site Address
TBD
Start
/
End
/2011
Architect
Contractor
Client / Contact
Cost
$ 21,000,000
Progress
0%
Related Links
Brennan HS
2010
$
89,751,853
10%
Project Details
Site Address
_____________ Cottonwood Way
San Antonio, TX 78253
San Antonio, TX 78253
Start
12/2007
End
6/2010
Architect
Marmon Mok
Contractor
Bartlett-Cocke, Inc.
Client / Contact
Victor G. Valdez
Cost
$ 89,751,853
Progress
10%
Related Links
Garcia MS
2009
$
39,142,776
28%
Project Details
Site Address
14900 Kyle Seale Parkway
San Antonio, TX 78255
San Antonio, TX 78255
Start
9/2007
End
6/2009
Architect
Noonan Rittimann
Contractor
Joeris
Client / Contact
Thomas Curiel
Cost
$ 39,142,776
Progress
28%
Related Links
Hoffmann ES
2009
$
18,945,000
43%
Project Details
Site Address
12118 Volunteer Parkway
San Antonio, TX 78253
San Antonio, TX 78253
Start
10/2007
End
5/2009
Architect
PBK
Contractor
Bartlett-Cock, Inc.
Client / Contact
Marilyn Sevedge
Cost
$ 18,945,000
Progress
43%
Related Links
Kuentz ES
2009
$
20,437,518
35%
Project Details
Site Address
12303 Leslie Road
Helotes, TX 78023
Helotes, TX 78023
Start
12/2007
End
6/2009
Architect
O'neil Conrad Oppelt
Contractor
Client / Contact
Thomas Curiel
Cost
$ 20,437,518
Progress
35%
Related Links
Langley ES
2009
$
19,488,058
10%
Project Details
Site Address
600 Stevens Parkway
San Antonio, TX 78253
San Antonio, TX 78253
Start
2/2008
End
6/2009
Architect
Garza Bomberger
Contractor
Client / Contact
Kathy Weaver
Cost
$ 19,488,058
Progress
10%
Related Links
Lieck ES
2011
$
21,000,000
0%

Project Details
Site Address
TBD
Start
/
End
/2011
Architect
Contractor
Client / Contact
Cost
$ 21,000,000
Progress
0%
Related Links
* Figures Represent General Construction Costs Only